Requirement

In anticipation of increased seasonal demand, our client urgently needed a storage facility for high value pre-packed beverage products at the company’s regional UK distribution facility. As the products were destined for use in multiple retail outlets it was imperative the product packaging was protected from the elements at all times before onward distribution to the retail shop floors.

Solution

Two buildings were installed; 20.00m x 85.00m and a 23.50m x 85.00m on 6.20m eaves, incorporating an 85.00m gutter link which created an internal open covered space of 3,697m².

The temporary warehouse building was supplied with an energy efficient Thermo insulated roof, security steel clad side walls, internal lighting providing a minimum lighting level of 150LUX, 4 x electric steel roller shutter doors, 4 x high-speed shutter doors, one situated in the gable and one along the eave and 18 personnel access door units.

Crucially, the temporary building was designed to fully comply with the site specific wind and snow loading requirements according to BS6399, making the building fully compliant with UK Building Regulations.

Benefit

To accommodate high seasonal demand the need for extra temporary space has traditionally been found off-site. Our client benefited by getting the essential space needed to capitalise on the busy forthcoming season, but were also able to keep everything under one roof. Not only has this avoided additional transport costs, but it means the operation remains slick and efficient. And, critically, customer’s happy with fast lead times and order requirements always in stock.